Project: Blocked Drain Customer: Unnamed Leading Insurer Sector: Insurance Location: unable to disclose The Project The Customer Ownership Team took a call from a leading insurer regarding a collapsed drain, which was causing a policyholder’s toilet to back up, leaving them without toilet facilities. The insurance claim handler considered it urgent and a priority to rectify. The Solution UKDN […]
Pipe repair excavation – Claire and Chris Hawes
Project: Pipe repair excavation Client: Claire and Chris Hawes The Challenge The blockage in the pipe was very close to the back of the house. This meant care was needed to avoid damaging the foundations. Because the pipe ran from under a basement, it was also three metres underground, so a lot of material had to be […]
Blocked wildlife tunnel – Heathrow Express
Project: Drain repair and reline Customer: Network Rail Sector: Rail Location: London Background Heathrow Express is an airport rail link between London Heathrow Airport and London Paddington station. The service is operated by the Heathrow Express Operating Authority, a wholly owned subsidiary of BAA. It is not legally part of the National Rail system, even though it shares track […]
Ground breaking no-dig project keeps Liverpool Street Crossrail station on track at Moorgate
Project: Large diameter UV lining Customer: BAM Nuttall Kier JV Sector: Rail Location: Moorgate, London. The challenge UKDN Waterflow (LG) was commissioned to install the largest diameter ultra-violet (UV) cured liner ever installed in Western Europe. The task was needed to strengthen a 1440mm diameter sewer located just seven metres from the path of Crossrail, the new east-west […]
Midgham Station – No Dig versus conventional drain re-instatement
Project: No dig track drainage renewal Customer: Amey Colas Western, for Network Rail Sector: Rail Location: Midgham, Berkshire The challenge The client wanted to renew over 250m of track drainage at Midgham Station. It commissioned us to carry out a CCTV camera drainage survey of current system, and then asked us to submit a plan for a technical solution. […]
Pipe Jacking solution solves culvert collapse
Project: Culvert pipe jacking Customer: Network Rail Sector: Rail Location: Filton, Bristol The challenge A six-feet wide and 90m-long section of culvert, made from corrugated steel, collapsed. It caused localised flooding that threatened the operations of the country’s largest NHS blood bank. Network Rail put in emergency over-pumping, with a capacity of more than seven million litres per […]
Preparing for Crossrail groundwork by protecting a 120m Sewer
Project: Sewer protection Customer: Thames Water Sector: Utilities Location: Mayfair, Central London The challenge We were commissioned to install two pipe liners to strengthen a sewer so it was protected from potential movements caused by tunnelling under Davies Street, Mayfair, for Crossrail, the new east-west rail line though London. The design and shape of the sewer, plus access limitations, […]
Routine CCTV work uncovers need for major Fulham reinforcement works
Project: Sewer reinforcement Customer: Thames Water Sector: Utilities Location: Fulham, West London The challenge While carrying out a routine survey, one of our CCTV drainage survey crews identified a problem that resulted in the need for an emergency project to reinforce 70 metres of Victorian brick-built sewer running one metre from live railway lines. The survey team, carrying out […]
Unique stainless steel structural design protects important sewer in London
Project: Crossrail steel structural liner Customer: Crossrail Sector: Rail Location: East London The challenge Crossrail is a 118-kilometre (73-mile) east-west railway line being built in London and the Home Counties of Berkshire, Buckinghamshire and Essex. One of scheme’s 7.1-metre-diameter tunnel boring machines was due to come within 0.5m of the Ham sewer in East London, operated by Thames Water […]
Drainage Accelerated Maintenance Project – Resolving high priority drainage issues to reduce track related risks
Project: Priority drainage programme Customer: Network Rail Sector: Rail Location: South West England The challenge UKDN Waterflow (LG) was commissioned to carry out a number of high priority projects under the Drainage Accelerated Maintenance Project. This was a programme to rapidly improve drainage on areas of line where drainage conditions impacted greatest on customer service, for example the need […]