Blocked wildlife tunnel – Heathrow Express

Blocked Wildlife tunnel HeX

Project: Drain repair and reline

Customer: Network Rail

Sector: Rail

Location: London

Background

Heathrow Express is an airport rail link between London Heathrow Airport and London Paddington station. The service is operated by the Heathrow Express Operating Authority, a wholly owned subsidiary of BAA. It is not legally part of the National Rail system, even though it shares track with National Rail trains for much of its journey and terminates at a London mainline station.

The Challenge

Working through a Tier 1 contractor UKDN Waterflow was contacted regarding the location of a collapsed wildlife tunnel underneath the tracks, buried beneath significant vegetation growth.

The tunnel, suspected to have been approximately 50metres in length, straddled the track but on the opposite side the embankment was overgrown with vegetation and could not be easily located.

Locating the tunnel would require access along the Heathrow Express line cess and then walking down the embankment. As the access is along the live tracks, any person working on the project would need to be would have to be Personal Track Safety (PTS) trained.

Network Rail raised concerns with regard to the alignment of the tunnel and this would need to be considered with any remedial work. If there was a bend in the tunnel there was a risk of drilling through the existing pipe. If there was a large hole in the roof of the pipe there was a risk of the drill being diverted through the hole whilst going through any blockage.

Blocked Wildlife tunnel HeX - UKDN Waterflow

Our Solution

UKDN Waterflow provided a team to clear the vegetation from the embankment and locate the Wildlife tunnel. Access to the other side was restricted to pedestrians only, so all of the works were completed from one side. This also eliminated the need to obtain access from Network Rail.

As suspected we found that the existing tunnel had collapsed. Our solution involved accessing the track during pre-booked minor possessions when trains were not running, and these occurred at night.

Rehabilitation of the tunnel, approximately four metres below rail level, involved drilling through the existing collapsed sections, following the drill head with a locater to ensure accuracy, and then installing a 150mm High Density Polyethylene (HDPE) duct by pulling it back with the drill head. This part of the solution was completed during the day, allowing the rail link to remain in service.

Result

All works were completed on time and within budget.

As our PTS staff were trackside we were also asked to assist in some cable installation, pulling the cable through and laying in a 50 metre trench before backfilling, and removing the equipment.